logo
MENU

Dredging Project

Information and updates related to the 2024 dredging project on lakes Wildwood and Tanglewood.

Wildwood

Jump to Latest Updates

We have started the dredging project on Wildwood. The vendor began in area 7, aiming to remove 1,166 cubic yards of material. However, after just 75 yards, it was found that the equipment was too large for the narrow cove.

Area 7


A smaller barge is needed to complete the work in this area. As a result, dredging in this and several other coves will be delayed to accommodate the need for smaller equipment. We will prioritize finishing all coves that can accommodate the larger barge and machinery first.

Area 7 to Area 4
The vendor moved to area 4 (adjacent to Lake Wildwood's Beach 2) and worked there until Monday, September 9, successfully removing 2,222 cubic yards of sediment and other materials.

Area 4 to Areas 2 and 3
Updated 9/20
Beginning Monday, September 9th, the vendor has moved to areas 2 and 3 where they will remove over 4,000 cubic yards of silt and material.

They have begun work in area 3 (adjacent to lots 1260-1263, 1265, and 1266) and area 2 (adjacent to lots 271-274) until the beginning of next week (September 15th).

Friday, September 20th Update
Areas 2 & 3 to Areas 5, 7 & 9

The dredging crew had a busy week, focusing on areas 2 and 3. They removed nearly 4,000 cubic yards of material. A big thank you to everyone who helped move boats and floating docks to improve access. There's about half a day's work left in area 2, with around 450 cubic yards remaining.

To boost production, the vendor has added another tug and a double hopper. Today, the smaller barge and equipment were placed on the water in preparation for work in the tighter cove entrances that still need attention. Starting Monday afternoon (9/23), the vendor will move to area 5 to remove an additional 1,111 cubic yards of material.

As the project winds down, the crew will be focusing on smaller coves. The areas scheduled for work next week also include area 7 (1,166 cubic yards) and area 9 (435 cubic yards). We appreciate all the feedback and patience during this process. Significant progress has been made in restoring the lake and its coves to their former glory. Stay tuned for more updates and potential changes as the project continues for another 10-14 days.

Area 5 Map Area 9 Map


Monday, September 30th Update | Current Location
Areas 1, 6, and 9
The vendor completed work on Area 2 this week and has since transitioned to Areas 5 and 7. Due to narrowing conditions in these areas, they were able to make progress but had to stop before reaching the full planned extent. Currently, work is continuing in Area 9 (Breezy Point/Winter Haven Cove).

The plan for this week is to finish Area 9, move on to Area 1 (Chevy Chase/Lake Wildwood Dr. Cove, South near T-43) and continue through the end of the week, before proceeding to Area 6 (Walnut Hill/Lake Wildwood Dr. Cove, North-East near T-18). They may also use both barges and machines to work simultaneously on Area 8 (Beach 1 Marina Cove).

We have an estimated 4,579 contracted yards left to remove, which puts us about two-thirds of the way through the project.

Area 1

Area 1 Map

Area 6

Area 6 Map

Area 9

Area 9 Map

Dredging Begins on Lake Wildwood Dredging Begins on Lake Wildwood Dredging Begins on Lake Wildwood Dredging Begins on Lake Wildwood

Tanglewood

The dredging on Lake Tanglewood is now complete! We successfully removed a total of 10,500 cubic yards of material from the A-Basin (Boat Launch) and B-Basin areas of the lake. This project has restored water depth to six feet in areas that were previously less than two feet deep. While the results vary across different sections, the main channels at each end have seen significant improvement.

Tanglewood Dredge Scoops Soil and Sediment from Lake Tanglewood Dredge Scoops Soil and Sediment from Lake

The boat launch that was damaged during the first phase of the project will soon be replaced. We’ve selected a vendor and approved the quote for the replacement. We expect this work to be completed by the beginning of October.

September 30th Update
Repairs are nearly completed to the Tanglewood launch!

Dredging FAQ: Understanding the Process and Benefits

What is dredging?
Dredging is the process of removing built-up soil, sediment, and debris from the bottom of a lake or waterway. Over time, natural processes like erosion and runoff can cause sediment to accumulate, especially in coves and shallow areas. This buildup can impact the health and usability of a lake, reducing water depth, affecting fish habitats, and even leading to poor water quality.

Why are we dredging the coves?
Coves are more prone to sediment accumulation because they're often sheltered, leading to slower-moving water where soil and debris settle more easily. By dredging, we're clearing out years of built-up sediment to restore the natural depth and improve water flow. This helps to maintain a cleaner, healthier lake for both wildlife and recreational use.

How does dredging work?
Imagine a giant underwater vacuum cleaner! Specialized equipment is used to carefully remove the sediment from the lakebed. The material is then either pumped to a disposal site or collected for safe removal. Dredging is done methodically to ensure minimal disruption to the surrounding environment.

What are the benefits of dredging?
Improved Water Quality: Removing excess sediment helps reduce pollutants and prevents the water from becoming murky.

Restoring Depth: Sediment buildup reduces the depth of the lake, making some areas unusable for boating or swimming. Dredging restores these areas for recreational fun.

Better Fish Habitats: Many fish species rely on deeper, cleaner water to thrive. By clearing out sediment, we’re creating a healthier environment for fish populations.

Preventing Future Problems: Excess sediment can lead to flooding or other water management issues. Dredging helps maintain proper water flow and reduces the risk of these problems.

Did You Know?
Some lakes can see up to 2-5 inches of sediment build up per year! Over time, this adds up and can significantly alter the landscape of the lake.

In short, dredging is like giving our lake a little TLC—keeping it clean, healthy, and enjoyable for everyone! Whether you love fishing, boating, or just relaxing by the water, dredging ensures our lake remains a beautiful, vibrant resource for years to come.