logo
MENU

Dredging Project

Information related to the 2024 dredging project on lakes Wildwood and Tanglewood.

Wildwood

Jump to Final Update

We have started the dredging project on Wildwood. The vendor began in area 7, aiming to remove 1,166 cubic yards of material. However, after just 75 yards, it was found that the equipment was too large for the narrow cove.

Area 7


A smaller barge is needed to complete the work in this area. As a result, dredging in this and several other coves will be delayed to accommodate the need for smaller equipment. We will prioritize finishing all coves that can accommodate the larger barge and machinery first.

Area 7 to Area 4
The vendor moved to area 4 (adjacent to Lake Wildwood's Beach 2) and worked there until Monday, September 9, successfully removing 2,222 cubic yards of sediment and other materials.

Area 4 to Areas 2 and 3
Updated 9/20
Beginning Monday, September 9th, the vendor has moved to areas 2 and 3 where they will remove over 4,000 cubic yards of silt and material.

They have begun work in area 3 (adjacent to lots 1260-1263, 1265, and 1266) and area 2 (adjacent to lots 271-274) until the beginning of next week (September 15th).

Friday, September 20th Update
Areas 2 & 3 to Areas 5, 7 & 9

The dredging crew had a busy week, focusing on areas 2 and 3. They removed nearly 4,000 cubic yards of material. A big thank you to everyone who helped move boats and floating docks to improve access. There's about half a day's work left in area 2, with around 450 cubic yards remaining.

To boost production, the vendor has added another tug and a double hopper. Today, the smaller barge and equipment were placed on the water in preparation for work in the tighter cove entrances that still need attention. Starting Monday afternoon (9/23), the vendor will move to area 5 to remove an additional 1,111 cubic yards of material.

As the project winds down, the crew will be focusing on smaller coves. The areas scheduled for work next week also include area 7 (1,166 cubic yards) and area 9 (435 cubic yards). We appreciate all the feedback and patience during this process. Significant progress has been made in restoring the lake and its coves to their former glory. Stay tuned for more updates and potential changes as the project continues for another 10-14 days.

Area 5 Map Area 9 Map


Monday, September 30th Update
Areas 1, 6, and 9
The vendor completed work on Area 2 this week and has since transitioned to Areas 5 and 7. Due to narrowing conditions in these areas, they were able to make progress but had to stop before reaching the full planned extent. Currently, work is continuing in Area 9 (Breezy Point/Winter Haven Cove).

The plan for this week is to finish Area 9, move on to Area 1 (Chevy Chase/Lake Wildwood Dr. Cove, South near T-43) and continue through the end of the week, before proceeding to Area 6 (Walnut Hill/Lake Wildwood Dr. Cove, North-East near T-18). They may also use both barges and machines to work simultaneously on Area 8 (Beach 1 Marina Cove).

We have an estimated 4,579 contracted yards left to remove, which puts us about two-thirds of the way through the project.

Area 1

Area 1 Map

Area 6

Area 6 Map

Area 9

Area 9 Map

Friday, October 18th Update | Project Finalization
It has been a very busy last four weeks on the Lake!

Totals are as follows for silt removal from our lakes:

Lake Tanglewood: 10,500 cubic yards
Lake Wildwood: 12,754 cubic yards
Grand Total: 23,254 Cubic yards

The Vendor is preparing to de-mobilize from the lake today and tomorrow with smaller equipment and a very large move out day planned for next Tuesday (October 22nd). There will be a large crane on site and 8 semi-trailers to remove and haul the rest of the equipment to their next destination.

The Marina will be closed from 7:00 AM - 5:00 PM Tuesday, October 22nd. Please be aware and patient during this move out.

I want to sincerely thank all members for their patience and support throughout this project. We've achieved great success, extending the life of our number one amenity: the two lakes.

We will complete any necessary road patching and install a barrier at the access road to the 52-acre dump site. We ask all members to please avoid this area and refrain from entering until the spoils have dried and can be safely spread across the field. This area is hazardous and should be avoided. We appreciate your understanding and look forward to potentially using this space again in the future. Thank you once again for your patience throughout this project.

Tanglewood

The dredging on Lake Tanglewood is now complete! We successfully removed a total of 10,500 cubic yards of material from the A-Basin (Boat Launch) and B-Basin areas of the lake. This project has restored water depth to six feet in areas that were previously less than two feet deep. While the results vary across different sections, the main channels at each end have seen significant improvement.

Tanglewood Dredge Scoops Soil and Sediment from Lake Tanglewood Dredge Scoops Soil and Sediment from Lake

The boat launch that was damaged during the first phase of the project will soon be replaced. We’ve selected a vendor and approved the quote for the replacement. We expect this work to be completed by the beginning of October. (update: project complete)

Dredging FAQ: Understanding the Process and Benefits

What is dredging?
Dredging is the process of removing built-up soil, sediment, and debris from the bottom of a lake or waterway. Over time, natural processes like erosion and runoff can cause sediment to accumulate, especially in coves and shallow areas. This buildup can impact the health and usability of a lake, reducing water depth, affecting fish habitats, and even leading to poor water quality.

Why are we dredging the coves?
Coves are more prone to sediment accumulation because they're often sheltered, leading to slower-moving water where soil and debris settle more easily. By dredging, we're clearing out years of built-up sediment to restore the natural depth and improve water flow. This helps to maintain a cleaner, healthier lake for both wildlife and recreational use.

How does dredging work?
Imagine a giant underwater vacuum cleaner! Specialized equipment is used to carefully remove the sediment from the lakebed. The material is then either pumped to a disposal site or collected for safe removal. Dredging is done methodically to ensure minimal disruption to the surrounding environment.

What are the benefits of dredging?
Improved Water Quality: Removing excess sediment helps reduce pollutants and prevents the water from becoming murky.

Restoring Depth: Sediment buildup reduces the depth of the lake, making some areas unusable for boating or swimming. Dredging restores these areas for recreational fun.

Better Fish Habitats: Many fish species rely on deeper, cleaner water to thrive. By clearing out sediment, we’re creating a healthier environment for fish populations.

Preventing Future Problems: Excess sediment can lead to flooding or other water management issues. Dredging helps maintain proper water flow and reduces the risk of these problems.

Did You Know?
Some lakes can see up to 2-5 inches of sediment build up per year! Over time, this adds up and can significantly alter the landscape of the lake.

In short, dredging is like giving our lake a little TLC—keeping it clean, healthy, and enjoyable for everyone! Whether you love fishing, boating, or just relaxing by the water, dredging ensures our lake remains a beautiful, vibrant resource for years to come.


Dredging Begins on Lake Wildwood Dredging Begins on Lake Wildwood Dredging Begins on Lake Wildwood Dredging Begins on Lake Wildwood